Solve Applications Modeled by Quadratic Equations

We solved some applications that are modeled by quadratic equations earlier, when the only method we had to solve them was factoring. Now that we have more methods to solve quadratic equations, we will take another look at applications.

Let’s first summarize the methods we now have to solve quadratic equations.

As you solve each equation, choose the method that is most convenient for you to work the problem. As a reminder, we will copy our usual Problem-Solving Strategy here so we can follow the steps.

We have solved number applications that involved consecutive even and odd integers, by modeling the situation with linear equations. Remember, we noticed each even integer is 2 more than the number preceding it. If we call the first one n, then the next one is n + 2. The next one would be n + 2 + 2 or n + 4. This is also true when we use odd integers. One set of even integers and one set of odd integers are shown below.

Consecutive even integersConsecutive odd integers 64,66,6877,79,81 n1steven integern1stodd integer n+22ndconsecutive even integern+22ndconsecutive odd integer n+43rdconsecutive even integern+43rdconsecutive odd integer

Some applications of odd or even consecutive integers are modeled by quadratic equations. The notation above will be helpful as you name the variables.

We will use the formula for the area of a triangle to solve the next example.

Recall that when we solve geometric applications, it is helpful to draw the figure.

In the two preceding examples, the number in the radical in the Quadratic Formula was a perfect square and so the solutions were rational numbers. If we get an irrational number as a solution to an application problem, we will use a calculator to get an approximate value.

We will use the formula for the area of a rectangle to solve the next example.

The Pythagorean Theorem gives the relation between the legs and hypotenuse of a right triangle. We will use the Pythagorean Theorem to solve the next example.

The height of a projectile shot upward from the ground is modeled by a quadratic equation. The initial velocity, v0, propels the object up until gravity causes the object to fall back down.

We can use this formula to find how many seconds it will take for a firework to reach a specific height.

We have solved uniform motion problems using the formula D = rt in previous chapters. We used a table like the one below to organize the information and lead us to the equation.

Image shows the template for a table with three rows and four columns. The first column is empty. The second column is labeled “Rate.” The third column is labeled “Time.” The fourth column is labeled “Distance.” The labels are written in the equation Rate times Time equals Distance. There is one extra cell at the bottom of the fourth column.

The formula D = rt assumes we know r and t and use them to find D. If we know D and r and need to find t, we would solve the equation for t and get the formula t=Dr.

Some uniform motion problems are also modeled by quadratic equations.

Work applications can also be modeled by quadratic equations. We will set them up using the same methods we used when we solved them with rational equations.We’ll use a similar scenario now.

Key Concepts

  • Methods to Solve Quadratic Equations
    • Factoring
    • Square Root Property
    • Completing the Square
    • Quadratic Formula
  • How to use a Problem-Solving Strategy.
    1. Read the problem. Make sure all the words and ideas are understood.
    2. Identify what we are looking for.
    3. Name what we are looking for. Choose a variable to represent that quantity.
    4. Translate into an equation. It may be helpful to restate the problem in one sentence with all the important information. Then, translate the English sentence into an algebra equation.
    5. Solve the equation using good algebra techniques.
    6. Check the answer in the problem and make sure it makes sense.
    7. Answer the question with a complete sentence.
  • Area of a Triangle
    • For a triangle with base, b, and height, h, the area, A, is given by the formula A=12bh.
      Image of a trangle. The horizontal base side is labeled b, and a line segment labeled h is perpendicular to the base, connecting it to the opposite vertex.
  • Area of a Rectangle
    • For a rectangle with length, L, and width, W, the area, A, is given by the formula A = LW.
      Image shows a rectangle. All four angles are marked as right angles. The longer, horizontal side is labeled L and the shorter, vertical side is labeled w.
  • Pythagorean Theorem
    • In any right triangle, where a and b are the lengths of the legs, and c is the length of the hypotenuse, a2 + b2 = c2.
      Image shows a right triangle with horizontal and vertical legs. The vertical leg is labeled a. The horizontal side is labeled b. The hypotenuse is labeled c.
  • Projectile motion
    • The height in feet, h, of an object shot upwards into the air with initial velocity, v0, after t seconds is given by the formula h = −16t2 + v0t.

Practice Makes Perfect

Solve Applications Modeled by Quadratic Equations

In the following exercises, solve using any method.

The product of two consecutive odd numbers is 255. Find the numbers.

Two consecutive odd numbers whose product is 255 are 15 and 17, and −15 and −17.

The product of two consecutive even numbers is 360. Find the numbers.

The product of two consecutive even numbers is 624. Find the numbers.

The first and second consecutive odd numbers are 24 and 26, and −26 and −24.

The product of two consecutive odd numbers is 1,023. Find the numbers.

The product of two consecutive odd numbers is 483. Find the numbers.

Two consecutive odd numbers whose product is 483 are 21 and 23, and −21 and −23.

The product of two consecutive even numbers is 528. Find the numbers.

In the following exercises, solve using any method. Round your answers to the nearest tenth, if needed.

A triangle with area 45 square inches has a height that is two less than four times the base Find the base and height of the triangle.

The width of the triangle is 5 inches and the height is 18 inches.

The base of a triangle is six more than twice the height. The area of the triangle is 88 square yards. Find the base and height of the triangle.

The area of a triangular flower bed in the park has an area of 120 square feet. The base is 4 feet longer that twice the height. What are the base and height of the triangle?

The base is 24 feet and the height of the triangle is 10 feet.

A triangular banner for the basketball championship hangs in the gym. It has an area of 75 square feet. What is the length of the base and height, if the base is two-thirds of the height?

The length of a rectangular driveway is five feet more than three times the width. The area is 50 square feet. Find the length and width of the driveway.

The length of the driveway is 15.0 feet and the width is 3.3 feet.

A rectangular lawn has area 140 square yards. Its width that is six less than twice the length. What are the length and width of the lawn?

A rectangular table for the dining room has a surface area of 24 square feet. The length is two more feet than twice the width of the table. Find the length and width of the table.

The length of table is 8 feet and the width is 3 feet.

The new computer has a surface area of 168 square inches. If the the width is 5.5 inches less that the length, what are the dimensions of the computer?

The hypotenuse of a right triangle is twice the length of one of its legs. The length of the other leg is three feet. Find the lengths of the three sides of the triangle.

The lengths of the three sides of the triangle are 1.7, 3, and 3.5 ft.

The hypotenuse of a right triangle is 10 cm long. One of the triangle’s legs is three times the length of the other leg. Find the lengths of the two legs of the triangle. Round to the nearest tenth.

A rectangular garden will be divided into two plots by fencing it on the diagonal. The diagonal distance from one corner of the garden to the opposite corner is five yards longer than the width of the garden. The length of the garden is three times the width. Find the length of the diagonal of the garden.

Image shows a rectangular segment of grass with fence around 4 sides and across the diagonal. The vertical side of the rectangle is labeled w and the horizontal side is labeled 3 w. The diagonal fence is labeled w plus 5.

The length of the diagonal fencing is 7.3 yards.

Nautical flags are used to represent letters of the alphabet. The flag for the letter, O consists of a yellow right triangle and a red right triangle which are sewn together along their hypotenuse to form a square. The hypotenuse of the two triangles is three inches longer than a side of the flag. Find the length of the side of the flag.

Image shows a square with side lengths s. The square is divided into two triangles with a diagonal. The top triangle is red and the lower triangle is yellow. The diagonal is labeled s plus 3.

Gerry plans to place a 25-foot ladder against the side of his house to clean his gutters. The bottom of the ladder will be 5 feet from the house.How far up the side of the house will the ladder reach?

The ladder will reach 24.5 feet on the side of the house.

John has a 10-foot piece of rope that he wants to use to support his 8-foot tree. How far from the base of the tree should he secure the rope?

A firework rocket is shot upward at a rate of 640 ft/sec. Use the projectile formula h = −16t2 + v0t to determine when the height of the firework rocket will be 1200 feet.

The rocket will reach 1200 feet on its way up at 1.97 seconds and on its way down at 38.03 seconds.

An arrow is shot vertically upward at a rate of 220 feet per second. Use the projectile formula h = −16t2 + v0t, to determine when height of the arrow will be 400 feet.

A bullet is fired straight up from a BB gun with initial velocity 1120 feet per second at an initial height of 8 feet. Use the formula h = −16t2 + v0t + 8 to determine how many seconds it will take for the bullet to hit the ground. (That is, when will h = 0?)

The bullet will take 70 seconds to hit the ground.

A stone is dropped from a 196-foot platform. Use the formula h = −16t2 + v0t + 196 to determine how many seconds it will take for the stone to hit the ground. (Since the stone is dropped, v0= 0.)

The businessman took a small airplane for a quick flight up the coast for a lunch meeting and then returned home. The plane flew a total of 4 hours and each way the trip was 200 miles. What was the speed of the wind that affected the plane which was flying at a speed of 120 mph?

The speed of the wind was 49 mph.

The couple took a small airplane for a quick flight up to the wine country for a romantic dinner and then returned home. The plane flew a total of 5 hours and each way the trip was 300 miles. If the plane was flying at 125 mph, what was the speed of the wind that affected the plane?

Roy kayaked up the river and then back in a total time of 6 hours. The trip was 4 miles each way and the current was difficult. If Roy kayaked at a speed of 5 mph, what was the speed of the current?

The speed of the current was 4.3 mph.

Rick paddled up the river, spent the night camping, and then paddled back. He spent 10 hours paddling and the campground was 24 miles away. If Rick kayaked at a speed of 5 mph, what was the speed of the current?

Two painters can paint a room in 2 hours if they work together. The less experienced painter takes 3 hours more than the more experienced painter to finish the job. How long does it take for each painter to paint the room individually?

The less experienced painter takes 6 hours and the experienced painter takes 3 hours to do the job alone.

Two gardeners can do the weekly yard maintenance in 8 minutes if they work together. The older gardener takes 12 minutes more than the younger gardener to finish the job by himself. How long does it take for each gardener to do the weekly yard maintainence individually?

It takes two hours for two machines to manufacture 10,000 parts. If Machine #1 can do the job alone in one hour less than Machine #2 can do the job, how long does it take for each machine to manufacture 10,000 parts alone?

Machine #1 takes 3.6 hours and Machine #2 takes 4.6 hours to do the job alone.

Sully is having a party and wants to fill his swimming pool. If he only uses his hose it takes 2 hours more than if he only uses his neighbor’s hose. If he uses both hoses together, the pool fills in 4 hours. How long does it take for each hose to fill the pool?

Writing Exercises

Make up a problem involving the product of two consecutive odd integers.

ⓐ Start by choosing two consecutive odd integers. What are your integers?

ⓑ What is the product of your integers?

ⓒ Solve the equation n(n + 2) = p, where p is the product you found in part (b).

ⓓ Did you get the numbers you started with?

Answers will vary.

Make up a problem involving the product of two consecutive even integers.

ⓐ Start by choosing two consecutive even integers. What are your integers?

ⓑ What is the product of your integers?

ⓒ Solve the equation n(n + 2) = p, where p is the product you found in part (b).

ⓓ Did you get the numbers you started with?

Self Check

ⓐ After completing the exercises, use this checklist to evaluate your mastery of the objectives of this section.

This table provides a checklist to evaluate mastery of the objectives of this section. Choose how would you respond to the statement “I can solve applications of the quadratic formula.” “Confidently,” “with some help,” or “No, I don’t get it.”

ⓑ After looking at the checklist, do you think you are well-prepared for the next section? Why or why not?

Adapted from Intermediate Algebra 2e by OpenStax (openstax.org), licensed under CC BY-NC-SA 4.0. Changes were made. License: CC-BY-NC-SA-4.0.

These eBooks are a prerelease and are not yet certified conformant with WCAG 2.1 AA or any other accessibility standard. Every page is built against an automated accessibility gate, and our target for the published editions is WCAG 2.2 Level AA. If something is unusable, please tell us.